1. Persons applying for a construction permit issued pursuant to this chapter shall pay a construction permit fee as follows:
- (1) Seven hundred fifty for a wastewater treatment plant if the design flow is less than five hundred dollars** thousand gallons per day;
- (2) Two thousand two hundred dollars for a wastewater treatment plant if the design flow is equal to or more than five hundred thousand gallons per day;
- (3) Seventy-five dollars for a sewer extension of less than one thousand lineal feet of pipe;
- (4) Three hundred dollars for a sewer extension equal to or more than one thousand lineal feet of pipe; or
- (5) Three hundred dollars for each sewage pumping station.
- 2. The applicant shall pay the highest appropriate fee pursuant to subdivisions (1) to (5) of subsection 1 of this section, but shall pay only pursuant to one subdivision regardless of the nature of the planned construction.
- 3. The commission may establish, by rule, general permits for construction and establish fees for such permits that shall not exceed the construction permit fees provided for in subsection 1 of this section.
4. Persons who apply for or possess an operator's certificate for treatment of wastewater or for concentrated animal feeding operation waste management shall pay fees of:
- (1) Forty-five dollars for an application for a certificate of competency, including an initial exam and the issuance of an initial certificate of competency;
- (2) Twenty dollars for an application for subsequent exams of the same certification type and level if the applicant fails the initial exam;
- (3) Forty-five dollars for an application for a renewal of a certificate of competency;
- (4) Forty dollars for an application for reciprocity with other certification programs; and
- (5) Twenty-five dollars for the issuance of a reciprocated certificate of competency.
(L. 1990 S.B. 582, A.L. 2000 S.B. 741)
*For effective and expiration dates for fees imposed by this section, see § 644.054.
**Word "dollars" does not appear in original rolls.