Mo. Code Regs. Ann. tit. 7, § 10-24.130
Modified Design-Build Procedures
Effective Feb 28, 2006sections 226.020, RSMo 2000 and 226.030 and 227.107, RSMo Supp. 2004.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006. *Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004; and 227.107, RSMo 2002Missouri Highways and Transportation Commission
PURPOSE: This rule describes the modified design-build selection procedures.
- (1) Modified design-build selection procedures, the lowest price technically acceptable source selection process, may be used for any project.
(2) The Request for Proposal (RFP) will clearly state the following:
- (A) The identification of evaluation factors and significant subfactors that establish the requirements of acceptability; and
- (B) That award will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for noncost factors.
- (3) Tradeoffs will not be permitted, unless the tradeoff is in accordance with 7 CSR 10- 24.110. However, the commission may incorporate cost-plus-time (A+B) bidding procedures, lane rental, or other cost-based provisions in such contracts.
- (4) Proposals will be evaluated for acceptability but not ranked using the noncost/price factors.
- (5) Exchanges may occur in accordance with 7 CSR 10-24.300 through 7 CSR 10-24.330.
AUTHORITY: sections 226.020, RSMo 2000 and 226.030 and 227.107, RSMo Supp. 2004.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006. *Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004; and 227.107, RSMo 2002.