Mo. Code Regs. Ann. tit. 20, § 4240-22.010
PURPOSE: This rule states the public policy goal that this chapter is designed to achieve and identifies the objectives that the electric utility resource planning process must serve.
(2) The fundamental objective of the resource planning process at electric utilities shall be to provide the public with energy services that are safe, reliable, and efficient, at just and reasonable rates, in compliance with all legal mandates, and in a manner that serves the public interest and is consistent with state energy and environmental policies. The fundamental objective requires that the utility shall—
(C) Explicitly identify and, where possible, quantitatively analyze any other considerations which are critical to meeting the fundamental objective of the resource planning process, but which may constrain or limit the minimization of the present worth of expected utility costs. The utility shall describe and document the process and rationale used by decision-makers to assess the tradeoffs and determine the appropriate balance between minimization of expected utility costs and these other considerations in selecting the preferred resource plan and developing the resource acquisition strategy. These considerations shall include, but are not necessarily limited to, mitigation of:
tain factors that will affect the actual costs associated with alternative resource plans;
stringent legal mandates that may be imposed at some point within the planning horizon; and
native resource plans.
AUTHORITY: sections 386.040, 386.250, 386.610, and 393.140, RSMo 2000.* This rule originally filed as 4 CSR 240-22.010. Original rule filed June 12, 1992, effective May 6, 1993. Amended: Filed Oct. 25, 2010, effective June 30, 2011. Moved to 20 CSR 4240-22.010, effective Aug. 28, 2019. *Original authority: 386.040, RSMo 1939; 386.250, RSMo 1939, amended 1963, 1967, 1977, 1980, 1987, 1988, 1991, 1993, 1995, 1996; 386.610, RSMo 1939; and 393.140, RSMo 1939, amended 1949, 1967.