Minn. Stat. § 216B.1615
Subd. 1. Definitions.
(c) "Electric vehicle" means any device or contrivance that transports persons or property and is capable of being powered by an electric motor drawing current from rechargeable storage batteries, fuel cells, or other portable sources of electricity. Electric vehicle includes but is not limited to:
(d) "Electric vehicle charging station" means a physical location deploying equipment that:
Subd. 2. Transportation electrification plan; contents.
(a) By November 1, 2023, and periodically as ordered by the commission, but at least every four years thereafter, a public utility must file a transportation electrification plan with the commission that may include but is not limited to elements that:
(2) promote the:
(b) A transportation electrification plan may include but is not limited to the following elements:
(2) investments and customer incentives offered by the public utility to support transportation electrification across all customer classes, including but not limited to investments and customer incentives to facilitate:
(ii) widespread access to publicly available and conveniently located electric vehicle charging stations, including through partnerships between public utilities and establishments that retail automotive fuel, and any Minnesota trade association predominantly composed of establishments that retail automotive fuel, provided that the establishments:
(A) collaborate with the public utility to determine optimal charging locations;
(B) operate 24 hours per day and are staffed at least 14 hours per day, excluding public holidays; and
(C) assume charging station operating and maintenance costs, while maintaining operating standards in a safe and efficient manner consistent with industry standards; and
(4) rate structures or programs that:
Subd. 3. Transportation electrification plan; review and implementation.
The commission may approve, modify, or reject a transportation electrification plan. When reviewing a transportation electrification plan, the commission must consider whether the programs, investments, and expenditures as a whole are reasonable and in the public interest, and are reasonably expected to:
Subd. 4. Cost recovery.
Notwithstanding any other provision of this chapter, the commission may approve cost recovery under section 216B.16, including an appropriate rate of return, of any prudent and reasonable investments made or expenses incurred by a public utility, including rebates for the installation of electric vehicle infrastructure, to administer and implement an approved transportation electrification plan.
Subd. 5. Pending filings.
This section shall not apply to any proposals designed to satisfy the objectives established in subdivision 2 that are part of a proceeding that is pending before the commission as of April 1, 2023. In those proceedings, the commission shall have full authority and discretion to accept, modify, or reject the utility's proposals in accordance with the provisions of this chapter extant at the time the public utility's proposals were initially filed in the proceeding. In its filing due November 1, 2023, a public utility that is a party in such a pending proceeding shall not be required under this section to file proposals to satisfy the objectives of subdivision 2 in addition to those accepted or modified by the commission in the pending proceeding.