Minn. Stat. § 473J.11
Subd. 1. Contracts.
(b) Unless the authority and the NFL team agree otherwise:
(c) The authority may enter into an agreement with the NFL team and any other entity relating to the design, construction, financing, operation, maintenance, and use of the stadium and related facilities and stadium infrastructure. The authority may contract for materials, supplies, and equipment in accordance with section 471.345, except that the authority may employ or contract with persons, firms, or corporations to perform one or more or all of the functions of architect, engineer, construction manager, or program manager with respect to all or any part of the design, construction, financing, operation, maintenance, and use of the stadium and stadium infrastructure under the traditional separate design and build, integrated design-build, construction manager at risk, or public/private partnership (P3) structures, or a combination thereof.
To the extent practicable, the agreement must provide that at least 25 percent of the materials, supplies, and equipment used in the construction, operation, maintenance, and use of the stadium and related facilities and stadium infrastructure, other than the material subject to section 473J.15, subdivision 11, paragraph (c), must be made or produced by Minnesota businesses.
(h) The construction manager or program manager may enter into contracts with contractors for labor, materials, supplies, and equipment for the construction of the stadium and related stadium infrastructure through the process of public bidding, except that the construction manager or program manager may, with the consent of the authority or the NFL team if the NFL team has assumed responsibility for construction:
Subd. 2. Changes.
Unless otherwise agreed to by the authority and the NFL team, if either party requests an agreed upon change in minimum design standards, and this change is responsible for requiring the project to exceed the stated budget, the requesting party is liable for any cost overruns or associated liabilities.
Subd. 3. Stadium design.
The stadium and stadium infrastructure shall be designed and constructed incorporating the following general program and design elements:
Subd. 4. Cost overruns, savings.