Me. Rev. Stat. tit. 38, § 480-O (2025)
Nothing in this article prohibits the rebuilding, replacement or new construction of a bulkhead, retaining wall or similar structure, provided that the applicant for a permit demonstrates to the department or municipality, as appropriate, that the following conditions are met.
1. Location The bulkhead or similar structure to be constructed, rebuilt or replaced is located along some or all of the north-northeasterly property lines of land abutting the Scarborough River from the jetty to the Scarborough town landing.
[PL 1987, c. 809, §2 (NEW).]
2. Termination The terminus of any bulkhead or similar structure, including any wing wall, unless connected to another bulkhead or similar structure, shall terminate at least 25 feet from any abutting property.
[PL 1987, c. 809, §2 (NEW).]
PL 1987, c. 809, §2 (NEW). PL 1989, c. 890, §§A40,B81 (AMD). PL 2019, c. 285, §15 (AMD).