Me. Rev. Stat. tit. 35-A, § 4503 (2025)
At least 30 days before beginning construction of an interstate natural gas pipeline within this State, the corporation shall file with the Secretary of State a certified copy of the certificate of public convenience and necessity issued to it under the Federal Natural Gas Act or, if the pipeline is intrastate, a certificate exhibiting the commission's authorization.
PL 1987, c. 141, §A6 (NEW).