Md. Code Regs. 21.11.02.09
After award of the contract, the procurement officer is authorized to verify the sources of supply of steel products that are to be incorporated into the work to be performed under that contract.
Authority: State Finance and Procurement Article, §§12-101 and 17-301—17-306, Annotated Code of Maryland
Effective date: July 1, 1981 (8:13 Md. R. II-5)
Regulation .01 amended as an emergency provision effective July 1, 1981 (8:13 Md. R. II-3); emergency status expired October 1, 1981 (Emergency provisions are temporary and not printed in COMAR)
Regulations .01 and .02 amended effective May 10, 1982 (9:9 Md. R. 912)
Regulations .02, .04--.08 amended effective January 9, 1989 (15:27 Md. R. 3138)
Annotation: COMAR 21.11.02.02B cited in Attorney General Opinion No. 81-001 (January 15, 1981) (cited to the previous codification at COMAR