Md. Code Regs. 21.10.04.08
C. If the contractor fails to respond, provides an inadequate response, or denies the procurement agency claim or the relief sought by the procurement agency in whole or in part, and the claim is not otherwise settled, the procurement officer shall prepare a recommended decision on the claim, which shall contain:
“This decision is the final action of this agency. This decision may be appealed to the Maryland State Board of Contract Appeals in accordance with COMAR 21.10.04.09. If you decide to take such an appeal, you must mail or otherwise file a written notice of appeal with the Appeals Board within 30 days from the date you receive this decision.”
G. Unless the procurement agency claim is remanded to the procurement officer, the decision of the reviewing authority:
(2) Shall be furnished to the contractor by:
Authority: State Finance and Procurement Article, §§12-101 and 15-201—15-223, Annotated Code of Maryland
Effective date: July 1, 1981 (8:13 Md. R. II-5)
Regulations .01—.03 repealed and new Regulations .01—.06 adopted effective January 9, 1989 (15:27 Md. R. 3138)
Regulation .01B amended effective October 18, 1999 (26:21 Md. R. 1631)
Regulation .02B amended effective October 6, 1997 (24:20 Md. R. 1405); January 24, 2000 (27:1 Md. R. 78)
Regulation .02D amended and E adopted effective October 27, 2003 (30:21 Md. R. 1530)
Regulation .04E amended effective October 6, 1997 (24:20 Md. R. 1405)
Regulation .06D amended effective December 25, 2000 (27:25 Md. R. 2284)
Chapter revised effective May 9, 2005 (32:9 Md. R. 849)
Regulation .02E amended effective April 7, 2008 (35:7 Md. R. 751)
Regulation .04C, D amended effective March 11, 2019 (46:5 Md. R. 310)
Regulation .04E amended effective April 7, 2008 (35:7 Md. R. 751)
Regulation .05C, D amended effective April 7, 2008 (35:7 Md. R. 751)
Regulation .09B amended effective April 7, 2008 (35:7 Md. R. 751)