Md. Code Regs. 21.05.13.07
The requirements in Regulations .05A(1) and (2) and C and .06A of this chapter do not apply to a master contract for construction that is procured and awarded under this chapter and states how task orders will be awarded and the maximum number of qualified contractors that will be awarded a master contractor agreement for construction.
Authority: State Finance and Procurement Article, §§12-101, 13-101, 13-102, 13-113, 13-114 and 14-303, Annotated Code of Maryland
Effective date: March 11, 2019 (46:5 Md. R. 310)
Regulation .05B amended effective May 2, 2022 (49:9 Md. R. 531)
Regulation .05D adopted effective September 18, 2023 (50:18 Md. R. 800)
Regulation .06H repealed effective May 2, 2022 (49:9 Md. R. 531)