- A. The construction manager warrants that the work will be completed at or below the GMP with provisions for change order adjustments for owner-directed work that is outside the agreed-upon GMP work scope and not otherwise covered by the contingency.
- B. The GMP shall be based on design documents that are not less developed than 50 percent construction documents for the applicable scope of work.
- C. The GMP shall be agreed to as an amendment to the contract between the procurement agency and the construction manager.
Authority: State Finance and Procurement Article, §§12-101 and 13-103—13-104, Annotated Code of Maryland
Effective date: August 23, 2010 (37:17 Md. R. 1186)