A. An application for a proposed transmission line or modification to an existing transmission line shall include:
- (1) An explanation of the need for the project in meeting demands for service;
- (2) A description of the effect of the project on system stability and reliability;
- (3) A description of the consequences if the project is delayed or not approved;
- (4) An explanation of the cost effectiveness of the project, including an estimate of capital cost and annual operating cost; and
- (5) A description of the impact of the project on the economies of the State.
- B. If requested by the Commission, an application for a proposed transmission line shall include a plan as defined under COMAR 20.79.01.02.
Authority: Public Utilities Article, §§2-121 and 7-205—7-208, Annotated Code of Maryland
Effective date: February 10, 1997 (24:3 Md. R. 189)
Regulation .01 amended effective November 8, 2004 (31:22 Md. R. 1598)
Regulation .02D amended effective November 8, 2004 (31:22 Md. R. 1598)
Regulation .03A amended effective November 8, 2004 (31:22 Md. R. 1598)