Upon completion of the electric supply procurement process under COMAR 20.52.04, a utility shall:
- A. Explain the methodology used to calculate the price for electric service under this subtitle;
- B. Calculate the price for each type of electric service offered to a customer under this subtitle;
- C. File tariffs with the Commission containing the methods of calculating the price for each service authorized by this subtitle at least 30 days, and if possible 2 months, before the effective date of the tariffs;
- D. Provide affected customers at least 30 days notice, and if possible 2 months notice, of new prices for electric service under this subtitle; and
- E. Post on the utility's internet website, the actual price payable each month for each service offered under this subtitle.
Authority: Public Utilities Article, §§2-113, 2-121, 5-101, and 7-510, Annotated Code of Maryland
Effective date: June 7, 2004 (31:11 Md. R. 857)