Md. Code Regs. 20.50.06.11
Generator output watt meters and watt-hour meters in the utility's generating station shall be tested according to a suitable schedule by comparison with the utility's standards but may not exceed the appropriate test intervals as required under COMAR 20.50.02.02.
Authority: Public Utilities Article, §§2-121, 5-101, 7-301, and 7-302, Annotated Code of Maryland
Effective date: May 22, 1942 (Order No. 38330)
Chapter revised effective May 18, 1960 (Order No. 54348)
Chapter revised effective June 1, 1965 (Order No. 55819)
Regulations .04A and .07F amended effective October 1, 1967 (Order No. 56893)
Regulation .04 amended effective January 23, 1981 (8:2 Md. R. 117)
Regulation .07B amended effective September 2, 1991 (18:17 Md. R. 1921)
Chapter revised effective June 2, 1997 (24:11 Md. R. 795)