Md. Code Ann., State Fin. & Proc. § 13-225
Payments retained
Effective Oct 1, 2004Added by Acts 2000, c. 621, § 1, eff. Oct. 1, 2000. Amended by Acts 2001, c. 29, § 1, eff. April 10, 2001; Acts 2002, c. 204, § 1, eff. Oct. 1, 2002; Acts 2004, c. 173, § 1, eff. Oct. 1, 2004.State of Maryland
(a)
- (1) In this section the following words have the meanings indicated.
- (2) “Payment security” has the meaning stated in § 17-101 of this article.
- (3) “Performance security” has the meaning stated in § 17-101 of this article.
(b)
- (1) If a contractor has furnished 100% payment security and 100% performance security in accordance with Title 17, Subtitle 1 of this article under a State procurement contract for construction, the percentage specified in the contract for retainage may not exceed 5% of the total amount.
- (2) In addition to retainage, a primary procurement unit and the Maryland Transportation Authority may withhold from payments otherwise due a contractor any amount that the unit reasonably believes necessary to protect the State's interest.
- (3) Retainage withheld by a primary procurement unit and the Maryland Transportation Authority may be deposited in an interest-bearing escrow account in accordance with § 15-108 of this article.
(c)
- (1) A contractor may not retain a percentage of payments due a subcontractor that exceeds the percentage of payments retained by the primary procurement unit or the Maryland Transportation Authority.
- (2) Paragraph (1) of this subsection may not be construed to prohibit a contractor from withholding any amount in addition to retainage if the contractor determines that a subcontractor's performance under the subcontract provides reasonable grounds for withholding the additional amount.
(d)
- (1) A subcontractor may not retain a percentage of payments due a lower tier subcontractor that exceeds the percentage of payments retained from the subcontractor.
- (2) Paragraph (1) of this subsection may not be construed to prohibit a subcontractor from withholding any amount in addition to retainage if the subcontractor determines that a lower tier subcontractor's performance under the subcontract provides reasonable grounds for withholding the additional amount.
- (e) If retainage has been placed in escrow under § 15-108 of this article, each payment of retainage shall include a pro rata portion of interest earned.
- (f) This section may not be construed to limit the application of the provisions of Title 17, Subtitle 1 of this article.
Added by Acts 2000, c. 621, § 1, eff. Oct. 1, 2000. Amended by Acts 2001, c. 29, § 1, eff. April 10, 2001; Acts 2002, c. 204, § 1, eff. Oct. 1, 2002; Acts 2004, c. 173, § 1, eff. Oct. 1, 2004.