(a)
- (1) In this section the following words have the meanings indicated.
- (2) “Construction contractor” means a person that performs or is hired to perform road construction work.
- (3) “Road construction work” means the construction, repair, paving, repaving, or grading of a public roadway.
- (b) Before beginning road construction work on a public roadway in the sanitary district in which a water, sewer, or stormwater management structure is installed, a construction contractor shall give notice to the Commission and the county of the proposed construction work.
(c) The notice:
- (1) shall include the proposed construction schedule and information about the location of construction to accomplish the purposes of this section;
- (2) except in emergency road repair situations, shall be given to the Commission and the county at least 7 days before road construction work begins; and
- (3) in an emergency road repair situation, shall be given to the Commission and the county as promptly as feasible under the emergency situation.
- (d) Unless allowed by the Commission or the county, as appropriate, a person may not disturb, remove, pave over, or repave over a manhole, valve, fitting, or other Commission water or sewer structure or county stormwater management structure.
Added by Acts 2010, c. 37, § 3, eff. Oct. 1, 2010.