- (a) In this subtitle the following words have the meanings indicated.
- (b) “Design/build contract” means a contract that provides for both architectural and engineering design services and construction services as a part of a single contract.
- (c) “Evaluated bid price” means the price of a bid after adjustment in accordance with objective measurable criteria.
(d) “Facilities construction contract” means a contract that provides services for the construction of:
- (1) a water or wastewater treatment plant;
- (2) a water or wastewater pumping station and related force mains in the pumping station site limits;
- (3) a water storage facility;
- (4) a wastewater storage facility;
- (5) a building for Commission purposes; or
- (6) a pipeline.
- (e) “Objective measurable criteria” means standards that enable the Commission to compare the economy, effectiveness, or value of the subject of the bids.
Added by Acts 2010, c. 37, § 3, eff. Oct. 1, 2010. Amended by Acts 2012, c. 140, § 1, eff. Oct. 1, 2012.