Md. Code Ann., Pub. Util. § 7-207.5
Dispatchable energy generation project or large capacity energy resource projects; certificate of public convenience and necessity; expedited timelines
Effective Jun 1, 2025Added by Acts 2025, c. 625, § 6, eff. June 1, 2025; Acts 2025, c. 626, § 6, eff. June 1, 2025.State of Maryland
(a)
- (1) In this section the following words have the meanings indicated.
- (2) “Construction” has the meaning stated in § 7-207 of this subtitle.
(3)
- (i) “Dispatchable energy generation project” means a generating station or energy storage device that is part of a proposal approved by the Commission under § 7-1206 of this title.
- (ii) “Dispatchable energy generation project” includes any associated infrastructure necessary to interconnect the generating station to the electric distribution system.
- (4) “Energy storage device” has the meaning stated in § 7-216 of this subtitle.
- (5) “Generating station” has the meaning stated in § 7-207 of this subtitle.
(6) “Large capacity energy resource” means a generating station that:
(i) on or before January 1, 2025:
- 1. has applied to PJM for interconnection approval; or
- 2. has been approved by PJM for interconnection;
- (ii) has a capacity rating equal to or greater than 20 megawatts after accounting for the effective load carrying capability; and
- (iii) is part of a proposal approved by the Commission under § 7-1206 of this title.
- (7) “Qualifying project” means a dispatchable energy generation project or large capacity energy resource project that has been approved by the Commission under § 7-1208 of this title.
- (b) This section applies only to an application for a certificate of public convenience and necessity for the construction of a qualifying project.
- (c) Unless a certificate of public convenience and necessity is first obtained from the Commission in accordance with this section or § 7-207 of this subtitle, a person may not construct a qualifying project.
- (d) A certificate of public convenience and necessity issued under this section bestows the same rights as a certificate of public convenience and necessity issued under § 7-207 of this subtitle.
(e) A person applying for a certificate of public convenience and necessity under this section shall:
- (1) at least 45 days before submitting an application under this section, notify the Commission and the Power Plant Research Program; and
- (2) unless otherwise specified under this section, complete all pre-application requirements before submitting an application.
(f)
- (1) Except as provided in paragraph (2) of this subsection, the timelines associated with the normal pre-application requirements under § 7-207 of this subtitle, including the requirements under COMAR 20.79.01.04 and COMAR 20.79.01.05, shall be shortened to 45 days for applications submitted under this section.
- (2) If the proposed location of a qualifying project is in an overburdened community or underserved community, as defined in § 1-701 of the Environment Article, the timeline for the pre-application requirements under COMAR 20.79.01.04 and COMAR 20.79.01.05 shall remain at 90 days.
- (g) Once five applications have been received under this section within a 2-month period, the Commission may delay processing any subsequent applications submitted under this section without impacting the timelines specified in this section.
(h)
(1) The Commission shall:
- (i) expedite all proceedings for the review and approval of a certificate of public convenience and necessity for a qualifying project; and
- (ii) take final action on a certificate of public convenience and necessity for a qualifying project not later than 295 days after the Power Plant Research Program determines that the application is complete in accordance with COMAR 20.79.01.10.
- (2) The Commission may extend the time to take final action on a certificate of public convenience and necessity under this section if an applicant fails to comply with the law, regulatory requirements, or Commission orders associated with obtaining a certificate of public convenience and necessity.
- (3) Notwithstanding any other law or regulation, in order to meet the required timelines for the issuance of a certificate of public convenience and necessity under this section, the Commission may review and determine whether to approve decommissioning plans for a qualifying project after the certificate of public convenience and necessity has been issued.
- (i) In evaluating an application for a certificate of public convenience and necessity under this section, the Commission may contract for the services of independent consultants and experts.
Added by Acts 2025, c. 625, § 6, eff. June 1, 2025; Acts 2025, c. 626, § 6, eff. June 1, 2025.