Md. Code Ann., Pub. Util. § 7-1224
Procurement of front-of-the-meter transmission energy storage devices; competitive process; procurement solicitations; deadlines and capacity limits
Effective May 12, 2026Added by Acts 2025, c. 625, § 3, eff. June 1, 2025; Acts 2025, c. 626, § 3, eff. June 1, 2025. Amended by Acts 2026, c. 353, § 5, eff. May 12, 2026.State of Maryland
- (a) The Commission shall, by regulation or order, establish a competitive process for the procurement of projects for the construction and deployment of front-of-the-meter transmission energy storage devices in the State.
(b)
(1)
- (i) On or before January 1, 2026, the Commission shall issue a procurement solicitation for applications for projects for the construction and deployment of front-of-the-meter transmission energy storage devices.
- (ii) Except as provided in subparagraph (iii) of this paragraph, the procurement solicitation shall be for 800 megawatts of cumulative energy storage capacity, as measured in effective nameplate capacity.
- (iii) The procurement solicitation may exceed 800 megawatts of cumulative energy storage capacity, as measured in effective nameplate capacity, if the Commission determines that the proposals are cost-effective and adequately support the goals established under this subtitle, including the goal of securing affordable, reliable electrical service for Maryland residents.
- (2) On or before October 1, 2026, the Commission shall issue a decision on whether to approve one or more proposals in accordance with § 7-1226(c) of this subtitle.
(3)
- (i) Except as provided in subparagraph (ii) of this paragraph, the transmission energy storage devices procured in accordance with this subsection shall be operational within 24 months after a project is selected by the Commission.
- (ii) The Commission may extend the operating deadline under subparagraph (i) of this paragraph for good cause shown.
(c)
- (1) On or before January 1, 2027, the Commission shall issue a second procurement solicitation for the procurement of projects for the construction and deployment of front-of-the-meter transmission energy storage devices.
(2)
- (i) Except as provided in subparagraph (ii) of this paragraph, the procurement solicitation shall be for 800 megawatts of cumulative energy storage capacity, as measured in effective nameplate capacity.
- (ii) The procurement solicitation may exceed 800 megawatts of cumulative energy storage capacity, as measured in effective nameplate capacity, if the Commission determines that the proposals are cost-effective and adequately support the goals established under this subtitle, including the goal of securing affordable, reliable electrical service for Maryland residents.
- (3) On or before October 1, 2027, the Commission shall issue a decision on whether to approve one or more proposals in accordance with § 7-1226(c) of this subtitle.
(4)
- (i) Except as provided in subparagraph (ii) of this paragraph, the transmission energy storage devices procured in accordance with this subsection shall be operational within 24 months after a project is selected by the Commission.
- (ii) The Commission may extend the operating deadline under subparagraph (i) of this paragraph for good cause shown.
Added by Acts 2025, c. 625, § 3, eff. June 1, 2025; Acts 2025, c. 626, § 3, eff. June 1, 2025. Amended by Acts 2026, c. 353, § 5, eff. May 12, 2026.