- (a) Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
- (b) Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.
Added by Acts 2010, c. 127, § 1, eff. Oct. 1, 2010.