(a) Within 30 days after the first meeting of the Commission after submission of a completed application, the Commission shall notify an applicant in writing:
- (1) whether the application for a license is approved or denied; and
- (2) of the reasons for denial, if the application is denied.
(b)
- (1) If the application is denied, the applicant, within 10 days after the notice of denial is mailed, may request a hearing.
- (2) The hearing shall be held in accordance with § 8-312 of this subtitle within 30 days after the date that the Commission receives the request.
- (3) The Commission shall make a decision within a reasonable time, but not later than 60 days after the hearing.
Added by Acts 1992, c. 4, § 2. Amended by Acts 2004, c. 244, § 1, eff. Oct. 1, 2004.
Formerly Art. 56, §§ 257, 260.