Mass. Gen. Laws ch. 149A, § 8
(a) For each building project procured pursuant to sections 1 to 9, inclusive, the public agency shall establish a trade contractor selection process for all sub-bid classes of work listed in section 44F of chapter 149 and all other sub-bid classes of work selected by the public agency for the project, provided the sub-bid work meets or exceeds the threshold sum identified in subsection (1) of section 44F of chapter 149. The selection process for the trade contractors shall conform to the requirements set out in subsections (b) to (k), inclusive, of this section. The public agency shall also establish a selection process for subcontractors who are not trade contractors as defined above. The selection process shall conform to the requirements of subsection (j) of this section. All trade contractors and subcontractors seeking to provide services in connection with the building project shall be prequalified in accordance with this section. The public agency may, consistent with established minority business enterprise and women business enterprise inclusion goals, provide an additional 5 points to the total score of each minority business enterprise and women business enterprise in the prequalification process as provided in subsection (e) of this section. The construction management at risk firm may submit its qualifications to bid on trade contract or subcontract work in accordance with this section; provided that the construction management at risk firm customarily performs the work for which it submits qualifications; provided further, that the construction management at risk firm must perform the work with employees on its own payroll; and provided further, that the construction management at risk firm meets all the requirements of the selection process.
All trade contracts entered into in accordance with this chapter shall be secured by performance and payment bonds in the full amount of the trade contract amount from a surety company licensed to do business in the commonwealth and whose name appears on United States Treasury Department Circular 570; provided that the bonds are subject to subsection (3) of section 44F of chapter 149.
(c) The construction management at risk firm shall provide to the public agency detailed information describing the work required for each trade contractor. This detailed information shall serve as the basis for an RFQ to be issued by the public agency. The public agency shall give public notice of trade contractor work on the building project and shall issue for each trade contract established under subsection (a) an RFQ which shall be used to solicit responses from eligible trade contractors and which shall be used to prequalify the trade contractors to participate on the building project; but, the public notice and solicitation shall include at a minimum:
(5) that the responders' names are to be posted, but that there shall be no public opening of responses.
All interested trade contractors shall be eligible to respond to the RFQ and participate in the prequalification process.
Each response submitted by a trade contractor in response to the RFQ shall be signed under pains and penalties of perjury. Financial information provided in response to the RFQ shall remain confidential and not be a public record as defined in section 7 of chapter 4 and shall not be open to public inspection, to the fullest extent possible under the law.
(e) The RFQ shall require only the information contained in subparagraphs 1 to 4, inclusive, of this paragraph, and shall identify the specific point allocation for each category and sub-category of information. Within each category of information, public agencies may use discretion in allocating points among the subcategories, consistent with the total points for the category.
(2) References (30 points; minimum of 15 required for approval):
(3) Capacity to Complete Projects (20 points; minimum of 10 required for approval):
(g) Trade contractors prequalified pursuant to subsection (f) shall be invited to submit a bid on the proposed building project pursuant to a Request for Bids for trade subcontracting services. The request for bids document shall include, without limitation, the following information:
(13) a trade contractor agreement form as set forth in this section including all exhibits.
Trade contractors submitting bids in response to the request for bids shall do so in accordance with the requirements contained in the request for bids package. Any bid which does not include the bid bond or affidavits required pursuant to this subsection or any response in which the information requested is incomplete, conditional, or obscure or which contains any additions not required in the request for bids package shall be rejected.
(k) When entering into a contract with a trade contractor selected to perform work pursuant to subsections (h) and (i), the trade contractor agreement shall be in the following form:
(1) The Trade Contractor agrees to furnish all labor and materials required for the completion of all work specified in Section No(s). ___ of the specifications for ___ (name of Sub–trade(s)) and the plans referred to therein and addenda No.___ for the ___ (project) all as prepared by ___ designer. All work shall be in accordance with the contract documents listed on Exhibit A; and the detailed Scope of Work listed on Exhibit B. The Construction Management At Risk Firm agrees to pay the Trade Contractor as full payment for all the work in Exhibit B the sum of $ . This price includes the following alternates: Nos. , , , ___.
(7) The following exhibits are incorporated into their subcontract:
Exhibit A: Contract Documents
Exhibit B: Detailed Scope of Work
Exhibit C: Project Schedule
(8) IN WITNESS WHEREOF, the parties hereto have executed this agreement the date and year first above-written.
SEAL
ATTEST ___ ___
Trade Contractor
SEAL
ATTEST ___ ___
Construction Management At Risk Firm
TRADE CONTRACTOR AGREEMENT
THIS AGREEMENT MADE THIS ___ DAY OF , 20 , by and between ___ a corporation organized and existing under the laws of ___a partnership consisting of ___ an individual doing business as ___ hereinafter called the ''Construction Management At Risk Firm'' and ___ a corporation organized and existing under the laws of ___ an individual doing business as ___ hereinafter called the ''Trade Contractor''.
WITNESSETH that the Construction Management At Risk Firm and the Trade Contractor for the considerations hereafter named, agree as follows: