Pre-filing Requirements for Consultation with DPP and OEJE
Effective Feb 27, 2026Mass. Register #1568MGL c. 164, §§ 69J, 69J1/4, 69T, 69U, 69VEnergy Facilities Siting Board
- (1) At least two weeks before the meeting(s) with DPP and OEJE at the start of the Pre-filing Outreach Period, the Applicant shall share a brief plain language description of the Project, the reason for the Project, location map, anticipated Project impacts and benefits, any alternative sites/routes under consideration, potential environmental impacts, a list of Key Stakeholders and Agency Consultations relevant to the Project, and a list of meetings already held or planned with Key Stakeholders and the Community. The Applicant may meet with DPP and OEJE individually or jointly.