- (1) Summary Report. An awarding authority shall submit to the Office of the Inspector General a summary report on the CM at Risk project within 70 days fromcompletion of the building project or termination of the contractor on the CM at Risk building project.
- (2) The summary report shallbe completed in a form prescribed by the Inspector General’s Office.
- (3) The summary report shall be a public record.
REGULATORY AUTHORITY
945 CMR 2.00: M.G.L. c. 149A, § 4.