310 C.M.R. 9.11
(1) Pre-application Consultation
(2) Application Review Schedules.
(b) For a nonwater-dependent use project, the applicant may elect one of four application options by submitting the selected category of application under the Timely Action and Fee Schedule at 310 CMR 4.00: Timely Action Schedule and Fee Provisions.
shall conduct its administrative completeness review and determine the application to be complete or request additional information. Within 60 days of determining the application to be complete, or 90 days from the close of the public comment period, whichever comes later, the Department shall issue the written determination under 310 CMR 9.14(1). The Department shall issue the final license under 310 CMR 9.14(5) within 45 days of the expiration of the appeal period or final decision, or 15 days from the date of the Governor’s signature, whichever is later. 2. Full Application. Within 45 days of receiving an application with all information identified in 310 CMR 9.11(3)(a), and 310 CMR 9.11(3)(b)1., 2., 6., and 7., and 310 CMR 9.11(3)(c)1. through 3., the Department shall assign a file number, make a determination of water-dependency under 310 CMR 9.12, conduct an administrative completeness review of the information received, and determine the application to be complete or request additional information. The Department shall issue a public notice under 310 CMR 9.13(1) upon determination that the application is complete. The public comment period shall begin at the notification date and end no less than 30 days and no more than 60 days from the notification date. The Department shall provide upon request the draft license conditions seven days prior to the public hearing. Within 20 days of the notification date, the Department shall hold the public hearing under 310 CMR 9.13(3). Within 60 days from the close of the public comment period and notification by the applicant that the public notice has been published, or the submission of the information identified in 310 CMR 9.11(3)(c)4., and 5., whichever is later, the Department shall issue the written determination under 310 CMR 9.14(1). The Department shall issue the final license under 310 CMR 9.14(5) within 45 days of the expiration of the appeal period or final decision, or 15 days from the date of the Governor’s signature, whichever is later. 3. Municipal Harbor Plan Application. For a project within an area governed by and in compliance with an Approved Municipal Harbor Plan approved under 301 CMR 23.00: Review and Approval of Municipal Harbor Plans and listed in 310 CMR 9.57, within 45 days of receiving an application containing the information identified in 310 CMR 9.11(3)(a) and (b), the Department shall assign a file number, make a determination of water-dependency under 310 CMR 9.12, and issue a public notice under 310 CMR 9.13(1). The public comment period shall begin at the notification date and end no less than 30 days and no more than 60 days from the notification date. Within 20 days of the notification date, the Department shall hold the public hearing under 310 CMR 9.13(3). Within 30 days of the close of the public comment period and notification by the applicant that the public notice has been published, the Department shall conduct its administrative completeness review and determine an application to be complete or request additional information. Within 45 days of determining an application to be complete, the Department shall issue a written determination under 310 CMR 9.14(1). The Department shall issue the final license under 310 CMR 9.14(5) within 45 days of the expiration of the appeal period or final decision, or 15 days from the date of the Governor’s signature, whichever is later. 4. Joint MEPA EIR Application. An applicant may initiate coordinated review under MEPA and 310 CMR 9.00 by specifying in the Environmental Notification Form (ENF) filing under 301 CMR 11.05: ENF Preparation and Filing the intent to pursue a joint filing. The Draft EIR submitted under 301 CMR 11.07(3) shall also include information to meet the application requirements of 310 CMR 9.11(3)(a) through (c)2. for pre- application review by the Department. Within 25 days of receipt of a Final EIR meeting the requirements of 310 CMR 9.11(3)(a) through (c)2., the Department shall assign a file number, make a determination of water-dependency under 310 CMR 9.12, conduct an administrative completeness review, and issue the text for the public notice under 310 CMR 9.13(1). The Department shall hold a public hearing within 20 days of the notification date or ten days after the date of the Secretary's Final Certificate, whichever is later. The public comment period shall begin at the notification date and end no less than 30 days and no more than 60 days from the notification date. The Department shall send to the applicant, within ten days of the close of the public comment period and receipt by the Department of notification from the applicant that the public notice has been published, whichever is later, any public comment submitted within the comment period for response and may request additional information or determine the application to be complete in accordance with 310 CMR 9.11(3)(c). Any response to comments provided by the applicant shall also be distributed by the applicant to all persons that
submitted comments during the public comment period. The Department shall issue the written determination under 310 CMR 9.14(1) within 30 days of receipt of the response to comments, or a determination that the application is complete, whichever is later. The Department shall issue the final license under 310 CMR 9.14(5) within 45 days of the expiration of the appeal period or final decision, or 15 days from the date of the Governor's signature, whichever is later.
(3) Filing and Completion of Application.
(b) The Department shall assign a file number to the project only after receipt of an application which includes the following information:
2. detailed description of the proposed project which identifies:
3. a set of plans containing at least the applicable information specified in 310 CMR 9.11(3)(a) through (c); the Department may accept appropriately-scaled preliminary plans in lieu of final plans certified in accordance with 310 CMR 9.11(3)(c)1., provided such preliminary plans are prepared by:
(c) The Department shall determine an application to be complete only if the following information has been submitted:
1. a set of final plans which are prepared in accordance with the format standards required for recording of licenses in the appropriate Registry of Deeds or Land Court for the district in which the licensed activity is to be performed; and which are certified by a Registered Professional Engineer or Land Surveyor, as deemed appropriate by the Department containing, at a minimum, the following:
3. final documentation relative to other state and local approvals which must be obtained by the project, including:
(4) Additional Information and Extensions.
(5) Expiration of Application
(b) With the exception of applications filed under 310 CMR 9.28, an application shall be presumed to have expired six months after any request for additional information by the Department unless the applicant submits information showing that: