Project Evaluation Report
Effective Oct 18, 2019Mass. Register #1402MGL c. 29C, § 18Massachusetts Department of Environmental Protection
- (1) Unless otherwise determined by the Department, the planning information required for projects receiving financial assistance pursuant to 310 CMR 45.00 shall be contained in a Project Evaluation Report.
(2) The Department will determine the required scope of a Project Evaluation Report based on the nature and duration of the proposed project. Unless otherwise determined by the Department, a complete Project Evaluation Report generally must include:
- (a) A description of the proposed project;
- (b) An analysis of the cost-effectiveness of the project and the alternatives considered;
(c) For the selected alternative, a concise description which addresses, at a minimum, the following areas:
- 1. the relevant design parameters for the project;
- 2. the estimated capital construction and operation and maintenance costs of the project (identifying possible federal, state, local, and other shares), and a description of the manner in which costs will be financed;
- 3. the cost impacts on users of the system; and
- 4. the institutional, financial, legal and management arrangements necessary for successful implementation of the project.
(d) A public participation program that includes, at a minimum:
- 1. a public informational meeting to discuss the project alternatives and their environmental impact; and
- 2. a subsequent public hearing on the selected proposed project, including its environmental impact.