- A. When required for acceptable completion of the pipe bursting process, the permittee shall provide for continuous sewage flow around the section(s) of pipe designated for the installation of replacement pipe.
- B. The pump bypass lines shall be of adequate capacity and size to handle the flow.
- C. Bypass pumping shall be considered incidental to the installation of the replacement pipe.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 48:381, et seq.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, Office of Highways/Engineering, LR 31:107 (January 2005), amended by the Department of Transportation and Development, Office of General Counsel, LR 51:1885 (November 2025).