A. In addition to the requirements enumerated above, the following requirements shall apply to cables installed parallel to the highway.
- 1. Installations shall occupy available space within the back 10 feet of the right-of-way (located on the side most distant from the traveled roadway), except where, upon showing of actual necessity, a permit is issued for another location.
- 2. Installations shall have a minimum earth cover of 36 inches.
- 3. Installations shall have a minimum clearance of
24 inches below existing or proposed drainage structures, unless otherwise approved by the department. - 4. There shall be no installation of cable within the median.
B. In general, installation of cable shall be as close to the right-of-way line as possible. The order of preferred locations for installing cable shall be:
- 1. between the control-of-access and the right-of-way;
- 2. between control-of-access right-of-way and shoulder if environmental conditions allow;
- 3. on longitudinal elevated structure.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 48:381.2.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, Office of Highways/Engineering, LR 25:2465 (December 1999).