- A. Temporary access connection permits may be granted for a period of time as specified on the permit. This time period shall be specified on the permit prior to issuance.
- B. Temporary access connection permits shall not be issued for a period of time to exceed one year.
- C. A temporary access connection permit may be extended or reissued as approved by the district engineer administrator.
- D. Applications for temporary access connection permits shall be accompanied by a bond per DOTD policies.
- E. All temporary access connections installed under a temporary access connection permit shall be constructed using non-permanent materials (i.e. aggregate). Concrete or asphalt should not be used for temporary access connections.
- F. The property owner shall be responsible for removal of any materials tracked onto the roadway by property operations on a daily and continual basis until such time that the temporary access connection is removed.
G. Temporary access connection permits may be issued where access from a state highway is needed on a short-term basis. Such instances may include, but are not limited to:
- 1. access during construction for a site where the future permanent access will be located on another roadway not within the state highway right-of-way;
- 2. use of an existing access connection during the permit application process for a change in land use.
- H. Temporary access connection permits to controlled access facilities shall not be allowed under any circumstances.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 48:344.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, LR 37:352 (January 2011).