- A. The provisions of this Section do not apply to single-family residential access connection permits, as described in the definitions Section of this Chapter.
- B. If the property is reconstructed/remodeled /redeveloped, the owner shall submit a request for a re-evaluation of the access connection(s). The re-evaluation shall contain all necessary information and documentation as required by DOTD in accordance with its policies, as well as a copy of the old access connection permit.
- C. If the property owner reconstructs the access connection, a request for re-evaluation shall be submitted. The DOTD reserves the right to make changes to the original permit during this process in order to improve safety and operations.
- D. If DOTD road maintenance and/or construction operations affect the condition or necessitate the reconstruction, improvement, modification, or removal of an existing access connection, a re-evaluation of the access connection geometrics, location, etc. may be performed by the district traffic operations engineer. The access connection permit may be re-issued according to the most current DOTD standards, and DOTD reconstruction efforts shall follow these standards. The cost to reconstruct the access connection to the right-of-way shall be borne by the DOTD. Any additional costs to improve on-site conditions may be borne by the property owner.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 48:344.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, LR 37:349 (January 2011), amended by HCR 9 of the 2013 Regular Session, amended by the Department of Transportation and Development, Office of Engineering, LR 40:1012 (May 2014).