- A. Applicant or his Engineer submits "Letter of Intent."
- B. Applicant or his Engineer submits "Pre-Application for Construction of Dam."
- C. Applicant publishes "Notice of Application" and a "Public Hearing(s)" is (are) held.
D. Applicant or his Engineer submits "Designs, Plans and Specifications" as follows and submits "Application for Construction of Dams."
- 1. "Impact (Hazard) Classification.
- 2. Determination of controlling design condition and associated storm runoff.
- 3. Setting of spillway and stilling basin widths and elevations, top of embankment elevation, and normal pool stage.
- 4. Plans, Specifications, Designs and other Submittals.
- E. The DOTD issues "Approval or Denial of Application"; Approval is an "Approval for Construction."
- F. Construction begins; Applicant or his Engineer performs "Construction Inspections."
- G. If "Deficiencies" are found by the DOTD, Applicant or Applicant's Engineer; then the Applicant or his Engineer shall correct the deficiencies.
- H. Supervision of Construction by the Owner.
- I. Applicant or his Engineer submits "Notice of Completion" and "As-Built Drawings" and revised "Application for construction of Dam."
- J. The DOTD issues "Certificate of Completion/Impoundment Permit."
- K. Applicant or his Engineer submits "Maintenance and Operation Procedures" for the DOTD's approval.
- L. Applicant or his Engineer submits "Emergency Preparedness Plan" for the DOTD's approval.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 38:24.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, Office of Public Works, LR 22:1241 (December 1985), repromulgated by the Department of Transportation and Development, Office of Public Works, LR 31:942 (April 2005).