- A. Each sponsoring authority designated as a recipient of program funds must enter into an agreement with DOTD prior to the initiation of construction of a project and awarding of funds. This agreement stipulates what must be followed during all construction phases of the project, operation and maintenance, as well as the sponsoring authorities' obligations under R.S. 38:91. Policies and procedures that must be adhered to are detailed in the Statewide Flood Control Program Procedural Manual for Funded Projects made available to all sponsoring authorities designated to receive program funding.
Authority Note
AUTHORITY NOTE: Promulgated in accordance with R.S. 38:90 et seq.
Historical Note
HISTORICAL NOTE: Promulgated by the Department of Transportation and Development, Office of Public Works, LR 5:579 (May 1985), repromulgated by the Department of Transportation and Development, Office of Public Works, LR 31:942 (April 2005), amended LR 35:2855 (December 2009), LR 46:1240 (September 2020).