This regulation shall apply only within the boundaries of groundwater management districts #2 and #5. (a) Except as specified in subsection (g), it shall be a violation of this regulation for the operator, owner, or person responsible to drill or construct either a cased or uncased cathodic protection borehole without first applying for and obtaining a permit to drill and construct a cathodic protection borehole.
(b) Each individual seeking a permit shall submit an application to the appropriate GMD office at least 60 days before planned construction, on a form furnished by the appropriate GMD. The permit application shall contain the following:
- (1) The name and address of the owner;
- (2) the quarter section, section, range, township, and county;
- (3) the distance from the borehole to the section's southeast corner, in exact footage;
- (4) the top and bottom depths of any freshwater aquifer;
- (5) the total borehole depth;
- (6) the number and depths of the anodes;
- (7) the top and bottom depths of the anode conductor or anode conductor grout; and
- (8) any other relevant information requested by the manager of the appropriate GMD.
- (c) Each manager of a GMD shall submit one copy of each cathodic protection borehole application upon which action has been taken to the production department of the conservation division within 10 days of approval.
- (d) The operator, owner, or person responsible shall notify the appropriate GMD office at least 72 hours before drilling each cathodic protection borehole.
- (e) When required by the manager of the appropriate GMD, the operator, owner, or person responsible shall submit a surface pit permit approved by the director of the conservation division with the application for a permit to drill and construct a cathodic protection borehole.
- (f) Drilling a cased or an uncased cathodic protection borehole without an approved permit shall be punishable by a penalty of up to $1,000. Drilling any cased or uncased cathodic protection borehole without providing notice to the appropriate GMD office in accordance with subsection (d) shall be punishable by a penalty of up to $1,000.
(g) No permit shall be required for a cathodic protection anode system that meets the following conditions:
- (1) Is constructed to a maximum depth below the land surface of 25 feet or less; and
- (2) does not penetrate an aquifer.
(Authorized by K.S.A. 55-152 and K.S.A. 2003 Supp. 82a-1028; implementing K.S.A. 55-152, K.S.A. 2003 Supp. 55-164, and K.S.A. 2003 Supp. 82a-1028; effective, T-82-1-21-04, Jan. 21, 2004; effective May 14, 2004.)