Kan. Admin. Regs. § 5-8-4
(c) If the total time allowed to construct the diversion works has been more than 16 months and fewer than 24 months, an extension of time shall be granted by the chief engineer only if the applicant meets the following criteria:
(d) If the total time allowed to construct the diversion works equals or exceeds 24 months, an extension of time may be granted only if the applicant demonstrates to the chief engineer that circumstances beyond the control of the applicant necessitate the extension of time.
(e)(1) The applicant shall file a notice of completion of diversion works and the statutorily required field inspection fee with the chief engineer no later than March 1 following the deadline to construct the diversion works. The notice of completion of diversion works shall be filed on a form prescribed by the chief engineer.
(2) If a water flowmeter has been required by the chief engineer as a condition of the permit, the applicant shall also file a notice of completion of installation of a water flowmeter on a form prescribed by the chief engineer. This form shall be due at the same time that the notice of completion of diversion works form is due.
(f)(1) The applicant shall be sent a notice by the chief engineer giving the applicant 30 days to show that the diversion works were completed within the time allowed in accordance with the terms, conditions, and limitations of the approval of application and to pay the field inspection fee, if it has not already been paid, under either of the following conditions:
(2) The permit shall be dismissed and its priority forfeited if the applicant fails to perform the following:
(Authorized by K.S.A. 82a-706a; implementing K.S.A. 82a-712, K.S.A. 82a-713, and K.S.A. 1999 Supp. 82a-714; effective Sept. 22, 2000.)