- (a) The district shall notify the division and the chief engineer when the district's approved project is complete and ready for final inspection.
(b) The notification to the division shall include the following:
- (1) The date of completion of the project; and
(2) an itemized list of all costs of the following:
- (A) Construction or rehabilitation; and
- (B) engineering inspections and geological investigations.
- (c) The district shall submit a request for final payment of state funds for the project on a form provided by the division, after the issuance of the certificate of completion by the chief engineer.
(Authorized by K.S.A. 2-1904 and K.S.A. 2-1915; implementing K.S.A. 2-1915; effective, T-86-43, Dec. 18, 1985; effective May 1, 1986; amended March 24, 2006; amended March 27, 2026.)