Ind. Admin. Code tit. 80, r. 9-4-1
Authority: IC 15-13-2-9
Affected: IC 15-13-2
Sec. 1. (a) Commission works contracts must be awarded under section 2 of this rule unless another method is authorized under this rule.
(b) At the discretion of the commission or commission representative, a duly certified or registered architect or licensed engineer may be utilized to approve the contract documents for a commission works project. A consulting engineer or architect may be retained by the commission by a professional services contract for the purpose of assisting in the administration of the provisions of this article.
(State Fair Commission; 80 IAC 9-4-1; filed Nov 7, 2016, 3:46 p.m.: 20161207-IR-080160210FRA; readopted filed Nov 15, 2022, 10:12 a.m.: 20221214-IR-080220291RFA)