Authority: IC 13-14-8-7; IC 13-15; IC 13-19-3
Affected: IC 13-18; IC 13-20; IC 36-9-30
Sec. 4. The soil components of the liner systems described in section 2 of this rule must meet the following requirements:
- (1) Be constructed on a slope of no less than two percent (2%) toward the leachate collection pipes.
- (2) Meet the specified thickness and hydraulic conductivity requirements of section 2 of this rule, as appropriate to the location of the proposed MSWLF unit.
(3) Be composed of lifts, each having a maximum thickness that:
- (A) is specified in the approved construction plan or is otherwise approved by the commissioner; and
- (B) in no case exceeds nine (9) inches after compaction.
(4) Have a design that adequately addresses the following factors:
- (A) Protection from damage due to uplift from hydrostatic forces.
- (B) Prevention of damage due to freeze/thaw and wet/dry cycles.
- (C) Any additional factors that are necessary to obtain an adequate soil component as specified in the construction plans or as determined by the commissioner.
(Solid Waste Management Division; 329 IAC 10-17-4; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1833; filed Mar 19, 1998, 11:07 a.m.: 21 IR 2776; filed Aug 2, 1999, 11:50 a.m.: 22 IR 3814; readopted filed Oct 16, 2024, 11:58 a.m.: 20241113-IR-329230812RFA)