Ind. Admin. Code tit. 329, r. 10-17-12
Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 12. (a) The protective cover must be installed in a single lift with no compaction. Quality control and quality assurance testing on the protective cover must include the following tests conducted at the indicated frequencies during installation of the protective cover:
(b) If the geotextile described in section 11(b) of this rule is used as an alternative to the protective cover, the project engineer shall ensure the following:
(1) Proper quality control and quality assurance testing is performed on the geotextile, and adequate results are obtained for the following tests, where applicable, or equivalent tests, performed in accordance with section 17 of this rule:
(2) The following criteria are addressed when determining the quality of the geotextile:
(Solid Waste Management Division; 329 IAC 10-17-12; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1838; filed Aug 2, 1999, 11:50 a.m.: 22 IR 3819; filed Feb 9, 2004, 4:51 p.m.: 27 IR 1818, eff Apr 1, 2004; readopted filed Oct 16, 2024, 11:58 a.m.: 20241113-IR-329230812RFA)