Ind. Admin. Code tit. 329, r. 10-17-10
Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 10. (a) The geosynthetic clay liner (GCL) must meet current industry design standards and any additional design standards necessary to obtain an adequate GCL, as specified in the construction plans or as determined by the commissioner.
(b) The project engineer shall ensure that adequate quality control and quality assurance procedures have been followed throughout all of the following operations:
(3) Installation of the geosynthetic clay liner, including:
(Solid Waste Management Division; 329 IAC 10-17-10; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1837; readopted filed Oct 16, 2024, 11:58 a.m.: 20241113-IR-329230812RFA)