Sec. 18. (a) A FESOP general permit may be issued subject to the following conditions:
(1) A FESOP general permit must:
(3) The commissioner may, after complying with the notice and opportunity for public participation provided under section 13 of this rule, issue a FESOP general permit covering numerous similar sources. In providing an opportunity for public comment, the commissioner shall publish notice as follows:
(b) For individual sources that wish to obtain FESOP general permit coverage, an applicant must do the following:
(3) Upon billing, submit an application fee in accordance with 326 IAC 2-1.1-7(f)(1). A source operating under a FESOP general permit issued under this section shall pay an annual operating fee in accordance with 326 IAC 2-1.1-7(f)(2). If an annual fee is being paid under a payment schedule established under IC 13-16-2-1, the fee must be paid according to that schedule. Establishment of a fee payment schedule must be consistent with the provisions of IC 13-16-2-1, including the determination that:
(c) A source that requests and is granted authority to operate under a FESOP general permit is subject to enforcement action for operation without a permit if the source is later determined not to qualify for the conditions and terms of the FESOP general permit.
(d) General permits may be issued for modifications of existing sources.
(Air Pollution Control Division; 326 IAC 2-8-18; filed Apr 22, 1997, 2:00 p.m.: 20 IR 2363; errata filed Jul 23, 2007, 4:19 p.m.: 20070815-IR-326070466ACA; filed Sep 28, 2011, 10:56 a.m.: 20111026-IR-326070286FRA; filed Mar 18, 2019, 2:36 p.m.: 20190417-IR-326170395FRA; readopted filed Oct 18, 2024, 2:09 p.m.: 20241113-IR-326230809RFA)