Authority: IC 14-12-3-13
Affected: IC 14-12-3-8
Sec. 4. (a) An applicant who is selected under this article to receive a grant must enter a project agreement with the department before the applicant is eligible to receive grant reimbursement.
(b) The project agreement must include the following:
- (1) The name and address of the applicant.
- (2) The project number as designated by the department.
- (3) The project title as designated by the department.
- (4) The date the director signed the project agreement; a statement that work begun before this date does not qualify for reimbursement, except as specified in the project agreement.
- (5) The expiration date when work must be completed in order to qualify for reimbursement.
- (6) The scope of the project that is eligible for reimbursement as determined by the commission.
- (7) Project costs that identify the sponsor's share and the grant share provided under the program.
(8) Terms needed to assure compliance with:
- (A) the standards and requirements of this article and any other applicable law;
- (B) project assurances under section 3 of this rule and other promises or representations made in the grant application; and
- (C) other requirements determined necessary by the department to address items that are unique to the project.
- (9) Standards for the maintenance of temporary construction signs on the property during the effective period of a grant under this article. These signs shall identify the nature and extent of participation in the project by the state.
- (10) Signatures needed to bind the department and the applicant to the terms of the project agreement.
(Natural Resources Commission; 312 IAC 26-2-4; filed Dec 3, 1997, 3:45 p.m.: 21 IR 1277; readopted filed Nov 17, 2004, 11:00 a.m.: 28 IR 1315; readopted filed May 26, 2010, 10:37 a.m.: 20100609-IR-312100161RFA; readopted filed Sep 27, 2016, 1:53 p.m.: 20161026-IR-312160147RFA; readopted filed May 18, 2022, 10:15 a.m.: 20220615-IR-312220030RFA)