Ind. Admin. Code tit. 105, r. 16.5-1-20
Authority: IC 8-23-2-6; IC 8-23-5-10
Affected: IC 8-23-5-10
Sec. 20. (a) This section applies if the operator's conduit preexisted the department's transportation project and the operator's conduit or broadband facilities conflicts with the project and needs to be relocated.
(b) An existing broadband facility that conflicts with a proposed highway improvement project must be relocated at the operator's expense. If the operator fails to relocate its broadband facility, any damage to the broadband facility as part of the highway improvement project is the sole responsibility of the operator. The department shall not be held liable for damage to a broadband facility that conflicts with a highway improvement project where the operator of the broadband facility was required to move the broadband facility and failed to relocate.
(c) Interruptions in service resulting from the department's transportation project are the sole responsibility of the operator.
(d) Except in an emergency, the department must give an operator not less than eighteen (18) months before a written notice to relocate.
(e) An existing broadband facility may remain in place if it does not conflict with the highway improvement project and complies with the following:
(Indiana Department of Transportation; 105 IAC 16.5-1-20; filed Jun 20, 2025, 1:31 p.m.: 20250716-IR-105250150FRA)