Ind. Code § 8-1-8.5-4
(a) As used in this section, "federal phaseout mandate" means any federal statutory or regulatory requirement that:
(c) In acting upon any petition for the construction, purchase, or lease of any facility for the generation of electricity, the commission shall take into account the following:
(1) The applicant's current and potential arrangement with other electric utilities for:
(3) With respect to a petition that:
(B) is submitted to the commission after June 30, 2021, and before January 1, 2025;
the impact of federal phaseout mandates on the estimated useful life of each proposed generating facility included in the petition, including depreciation expense associated with each facility.
(4) With respect to a petition that is submitted to the commission after June 30, 2023, whether the proposed construction, purchase, or lease of the facility will result in the provision of electric utility service with the attributes set forth in IC 8-1-2-0.6 , including:
(E) environmental sustainability;
as described in IC 8-1-2-0.6 .
(5) With respect to a petition that is submitted to the commission after December 31, 2029, whether:
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.9; P.L.180-2021, SEC.3; P.L.55-2023, SEC.4; P.L.126-2026, SEC.2.