Ind. Code § 8-1-37-11
(a) An electricity supplier that seeks to participate in the program established by the commission under section 10 of this chapter must apply to the commission:
(2) not later than a date specified by the commission in the rules adopted under section 10 of this chapter;
for approval to participate in the program.
(c) If the commission determines that:
(3) approving the application will not result in an increase to the retail rates and charges of the electricity supplier above what could reasonably be expected if the application were not approved;
the commission shall approve the application. If, however, the commission determines that the application does not meet the requirements set forth in this subsection, the commission shall reject the application. The electricity supplier that submitted the application under subsection (a) bears the burden of proving to the commission that the application meets the requirements set forth in this subsection.
As added by P.L.150-2011, SEC.16.