Ind. Code § 8-1-2.5-6.5
(a) As used in this section, "electricity supplier" means a public utility (as defined in IC 8-1-2-1 (a)) that furnishes retail electric service to customers in Indiana. The term does not include a utility that is:
(b) Before September 1, 2023, the commission shall commence a comprehensive study to consider the appropriate:
(2) requirements with respect to;
performance based ratemaking (as described in section 6(a)(2) of this chapter) for electricity suppliers.
(c) In conducting the study required by this section, the commission shall evaluate the following:
(4) The use of performance incentive mechanisms in conjunction with traditional cost-of-service ratemaking, to provide regulatory oversight and ensure that rewards and penalties are equitably balanced and do not:
(B) under-compensate electricity suppliers for costs and risks incurred;
as applicable.
(5) Best practices for allocating the costs, benefits, and risks associated with performance incentive mechanisms between:
(B) shareholders;
with affordability of service prioritized.
(d) In conducting the study required by this section, the commission may invite comments from:
(6) other stakeholders.
The commission may incorporate any comments received under this subsection in its report under subsection (e).
(e) The commission shall include in the annual report that the commission is required to submit under IC 8-1-1-14 before October 1, 2025, a report that includes the commission's analysis and recommendations on the topics outlined in subsection (c). The report required by this subsection must contain recommendations, supported by sufficient data and analysis from the commission's study under this section, with respect to the appropriate:
(2) requirements with respect to;
performance based ratemaking (as described in section 6(a)(2) of this chapter) for electricity suppliers, so as to enable the general assembly to fully evaluate the impact of performance based ratemaking on all classes of ratepayers, while considering the attributes of electric utility service set forth in IC 8-1-2-0.6 , including reliability, affordability, resiliency, stability, and environmental sustainability.
As added by P.L.55-2023, SEC.2.