Ind. Code § 36-9-41-1

Application

As added by P.L.81-2004, SEC.47. Amended by P.L.88-2009, SEC.16.

This chapter applies to the following:

  1. (1) A public work project that will cost the political subdivision not more than two million dollars ($2,000,000).
  2. (2) An eligible efficiency project that will cost not more than three million dollars ($3,000,000).

As added by P.L.81-2004, SEC.47. Amended by P.L.88-2009, SEC.16.