A works board may construct a private system on land owned by a private entity if:
- (1) the owner of the land has applied to the works board for construction of a system that the works board determines is appropriate for the sewage disposal needs of the location for which the application is made;
- (2) the owner of the land has supplied in the application to the works board sufficient information to prepare a preliminary resolution to approve construction of the system;
- (3) the works board has adopted a preliminary resolution approving construction of the system; and
(4) with respect to the system, the works board has, at the time the preliminary resolution is adopted, adopted and placed on file:
- (A) cross-sections;
- (B) general plans;
- (C) specifications; and
- (D) an estimate of the cost.
As added by P.L.7-2002, SEC.1.