Ind. Code § 36-9-27-83
(a) A subcontractor, laborer, or other person may file a claim with the board if:
(2) the subcontractor, laborer, or other person has not been paid.
The claim must be filed within sixty (60) days after the performance of the work or service or the furnishing of the material, and must state the amount due and describe the work done or materials furnished. The board shall withhold the amount of the claim from the final payment due the contractor unless the claimant files a written withdrawal of the claim with the board.
(d) This section does not relieve the surety on the contractor's bond from liability under its obligation as set forth in the bond.
[Pre-Local Government Recodification Citation: 19-4-7-8 part.]
As added by Acts 1981, P.L.309, SEC.101. Amended by P.L.127-2017, SEC.361.