Ind. Code § 36-9-27-77
(a) Whenever:
(2) the board determines that maintenance work shall be let by contract;
the board may contract for the work to be done as a whole or in sections.
(b) Except as provided in subsection (c), the board may not let a contract for the construction or reconstruction of a drain if the amount of the contract is more than ten percent (10%) above:
(e) Subject to IC 36-1-12-5 , the board may perform maintenance, construction, or reconstruction by its own work force without awarding a contract.
[Pre-Local Government Recodification Citation: 19-4-7-4.]
As added by Acts 1981, P.L.309, SEC.101. Amended by P.L.206-1984, SEC.7.