- (a) This section does not apply to the collection of an amount if a court determines under section 13 of this chapter that the enforcement authority is not entitled to the amount.
(b) If:
- (1) all or any part of the costs listed in section 12 of this chapter remain unpaid for any unsafe premises (other than unsafe premises owned by a governmental entity) for more than fifteen
- (15) days after completion of the work; or
(2) emergency action was taken under section 9 of this chapter, for more than fifteen (15) days after the costs of the emergency action have been affirmed by the hearing authority;
the enforcement authority may send notice under section 25 of this chapter to each person who held a known or recorded fee interest, life estate interest, or equitable interest of a contract purchaser in the unsafe premises. If the notice is sent, the enforcement authority shall also send notice to any mortgagee with a known or recorded substantial property interest. The notice must require full payment of the amount owed within thirty (30) days.
- (c) If full payment of the amount owed is not made less than thirty
- (30) days after the notice is delivered, the enforcement officer may certify the following information to the county auditor:
- (1) The name of each person who held a known or recorded fee interest, life estate interest, or equitable interest of a contract purchaser in the unsafe premises.
- (2) The description of the unsafe premises, as shown by the records of the county auditor.
- (3) The amount of the delinquent payment, including all costs described in section 12 of this chapter.
- (d) The county auditor shall place the total amount certified under subsection (c) on the tax duplicate for the affected property as a special assessment. The total amount, including accrued interest, shall be collected as delinquent taxes are collected.
- (e) An amount collected under subsection (d), after all other taxes have been collected and disbursed, shall be disbursed to the unsafe building fund.
- (f) A judgment entered under section 13, 19, 21, or 22 of this chapter may be certified to the auditor and collected under this section. However, a judgment lien need not be obtained under section 13 of this chapter before a debt is certified under this section.
As added by P.L.31-1994, SEC.13. Amended by P.L.169-2006, SEC.65; P.L.247-2015, SEC.47.